Executive Summary of Bid Evaluation Report
Project Title: Repairs and Maintenance Works to Port Infrastructure
(Terminal I, II, III)
Reference number of Procurement: Contract MPA 496/2021
The works are to be undertaken in two parts, “Part A” – Repairs and Upgrading Works and “Part B”- General Maintenance/Emergency Works within the Port Area.
PART A- Repairs and Upgrading Works
At Terminal I - Quays A, D, E incl. TFFP & Terminal II (Quays 1-4)
For Terminal III
The works also comprise of emergency maintenance to port infrastructure over a 1 year (365 days) period. The non-exhaustive list of works expected to be executed is described hereunder: - PART B- Maintenance Works within the Port Area
Bidder’ s Name |
Pricing at Bid Opening (MUR) (Excl. VAT) |
Responsive or not responsive (Yes/ No) |
Reasons why bids not responsive |
Sotravic Limited |
26,298,467.50 |
Yes |
- |
Prakash Foolchund |
21,924,998 |
Yes |
- |
Innov Jobs Enterprise Ltd |
19,863,660 (Discount of Rs 35,000 provided) |
Yes |
- |
Arwan Enterprise Ltd |
16,616,000 |
Yes |
- |
Kisten enterprise Ltd |
19,053,350 |
Yes |
- |
Tooling & Engineering Products Ltd |
19,226,964 |
Yes |
- |
EDCC Ltd |
18,134,395 |
Yes |
- |
Name |
Price at Bid Opening Mur (Excl. VAT) |
Bid Price after corrections Mur (Excl. VAT) |
Rank |
Sotravic Limited |
26,298,467.50 |
26,298,467.50 |
7 |
Prakash Foolchund |
21,924,998 |
21,924,998 |
6 |
Innov Jobs Enterprise Ltd |
19,863,660 (Discount of Rs 35,000 provided) |
19,863,660 (Discount of Rs 35,000 provided) |
5 |
Arwan Enterprise Ltd |
16,616,000 |
16,616,000 |
1 |
Kisten enterprise Ltd |
19,053,350 |
19,053,350 |
3 |
Tooling & Engineering Products Ltd |
19,226,964 |
19,226,964 |
4 |
EDCC Ltd |
18,134,395 |
18,134,395 |
2 |